Available land
Filter


Aniche | 1,2439 ha
Land in Aniche
Total surface area : 1,2439 ha
Available surface : 1,2439 ha
Availability : Immediately
Buildable height : 15 m
Infrastructures :
- Road: RD 645 access
- TGV Station: Somain (10 min)
- Canal access: Bouchain (15 min)
Utilities :
- Water: Connectible
- Electricity: Connectible
- Gas: Connectible
- Sanitation: Connectible
- Digital: Connectible
Comments :
Well placed land along a major road, close to a HSLV (High Service Level Bus) station, close to the city centre and close to other industrial and tertiary buildings

Épaux-Bézu / Bézu-Saint-Germain | 3 ha
Aera of 3 hectares in the Omois zone
Total surface area : 3 ha
Available surface : 3 ha
Cut out : 6 plots: 4,940 - 3,680 - 4,265 - 7,510 - 4,600 and 4,740m²
Availability : January 2023
Infrastructures :
- Road: A4 highway less than a kilometer away
- Air: No
- TGV Station: No
- Rail freight: No
- Canal access: No
- Sea port: No
- River port: No
Utilities :
- Water: yes
- Electricity: yes
- Gas: yes
- Sanitation: yes
- Digital: yes
Comments :
Plots of land available for industrial and service SMEs.

Isbergues | 10 ha
Isbergues industrial platform
Total surface area : 101 ha
Available surface : 10 ha
Cut out : from 5,000 to 20,000 m²
Availability : Immediately
Buildable height : 12 m
Infrastructures :
- Road: A26 (30 min), A21 (40 min)
- Air: Lille-Lesquin (1h), Bruxelles (2h15), Paris Charles de Gaulle (2h)
- TGV Station: Béthune (26 min)
- Rail freight: Internal rail network connected to the national network
- Sea port: Calais and Dunkirk 1h away
- River port: Béthune-Beuvry (26 min)
Utilities :
- Water: yes
- Electricity: yes
- Sanitation: yes
- Digital: fibre optic
Environmental standards : ICPE Zone
Comments :
The Isbergues industrial platform operates 365 days a year, with 5 companies and nearly 1,300 employees
In the regional assistance (AFR) zone

Villeneuve sur Aisne | 16 ha
Champ Rolland’s business centre
Total surface area : 38 ha
Available surface : 16 ha
Cut out : from 2,500m²
Availability : Immediately
Buildable height : 13 m
Infrastructures :
- Road: A26 less than a kilometer away, close to N2
- Air: Paris Roissy Charles de Gaulle (1h30)
- TGV Station: Reims Bezannes (30 min)
- Rail freight: Villeneuve sur Aisne SNCF station
- Canal access: Berry au Bac
Utilities :
- Digital: fibre optic

Bohain-en-Vermandois | 14 ha
Moulin Mayeux – Activity zone
Total surface area : 23 ha
Available surface : 14 ha
Availability : Immediately
Buildable height : 12 m
Infrastructures :
- Road: RD8 on site, St Quentin (25 min), Cambrai (30 min)
- Air: Lille Lesquin (1h30)
- TGV Station: Haute-Picardie (56 km)
- Rail freight: Bohain SNCF train station

Vermand | 6 ha
Champ des Lavoirs – zone of economic activities
Total surface area : 9 ha
Available surface : 6 ha
Availability : Immediately
Infrastructures :
- Road: A26/A29 (5 min)
- Air: Lille Lesquin (1h), Paris Charles De Gaulle (1h15), Paris Beauvais (1h30)
- TGV Station: Haute-Picardie (30 min)
- Canal: Saint Quentin’s canal
Utilities :
- Digital: high-speed internet access

Merville | 20 ha
Petits Pacaux Activity Zone
Total surface area : 20 ha
Available surface : 20 ha
Cut out : from 3,000 m²
Availability : 3 months
Infrastructures :
- Road: A25 (20 km)
- Air: Lilles-Lesquin (46 km), Paris Charles de Gaulle (206 km)
- TGV Station: Lille Europe (42 km)
Utilities :
- Water: drinkable and industrial
- Electricity: 1,000 kV possible
- Gas: MPB 4 bars network possible
- Sanitation: Collective sanitation, capacity of 12,000 inhabitant equivalent
- Digital: fibre optic
Comments :
In the regional assistance (AFR) zone

Douvrin | 10 ha
Artois Flandre Industrial Park
Total surface area : 23 ha
Available surface : 10 ha
Cut out : from 1 to 2 ha
Availability : Immediately
Buildable height : 20 m
Infrastructures :
- Road: North Motorway A1 LILLE / PARIS (20km), A26 between Troyes and Calais (11km), A21 between Lens and Valenciennes (7km), A25 between Lille and Dunkerque (15km), RN47 (2×2 lanes) on site
- Air: Lille Airport 25km, Charles de Gaulle Airport 188km
- TGV Station: Lens station (11km) and Lille station (28 km)
- Canal access: Yes
- Rail freight: Rail track into park
- Sea port: Dunkirk (100 km)
- River port: Delta3 (20km), Lille (32 km), Béthune (16 km)
Utilities :
- Water: Drinking water up to 1,300m3/day. Industrial water possible from canal
- Electricity: 7MvA source substation
- Gas: Total capacity of 300 Nm3/h available immediately
- Sanitation: Autonomous or separate, with water treatment plant equivilant to 27,000 inhabitants
- Digital: Fibre

Maroilles | 5,5 ha
Verts Paturages Business park
Total surface area : 5,5 ha
Available surface : 5,5 ha
Cut out : from 1,000 to 8,000m²
Availability : 2022/2023
Infrastructures :
- Road: next to D934
Utilities :
- Water: yes
- Electricity: yes
- Gas: no
- Sanitation: yes
- Sprinker : no
- Digital: Fibre optic
Comments :
Sale of serviced lots

Jenlain | 1,3 ha
Vallée de l’Aunelle Business Park
Total surface area : 1,3 ha
Available surface : 1,3 ha
Cut out : from 1,500 to 2,500m²
Availability : S1 2023
Infrastructures :
- Road: near to D649
Utilities :
- Water: yes
- Electricity: yes
- Gas: no
- Sanitation: yes
- Sprinker : no
- Digital: Fibre optic
Comments :
Sale of serviced lots

Ruitz | 41 ha
Ruitz Industrial Park
Total surface area : 266 ha
Available surface : 41 ha
Cut out : plots from 5 000 m² to 10 ha
Availability : Immediately
Buildable height : 15 m
Infrastructures :
- Road: A26 4kms, A21 10kms, A1 30kms away
- Air: Lille-Lesquin 50km, Roissy Charles de Gaulle 180km
- TGV Station: Béthune TGV station 6km
- Sea port: Dunkirk 90km
- River port: Béthune river port 6km
Utilities :
- Electricity: < 20,000 volts
- Digital: Fibre optic, high-speed internet
Comments :
Zone labelled as a “turnkey industrial site”
Multimodal platform: Delta3 at 40 km
The Ruitz park is home to 84 companies and over 3,200 employees
In the regional assistance (AFR) zone

Noeux-Les-Mines/Labourse | 42 ha
LogisterrA26
Total surface area : 55 ha
Available surface : 42 ha
Cut out : 240,000m² + 80,000m² + 50,000m² + 3 x 15,000m²
Availability : Immediately
Buildable height : 20 m
Infrastructures :
- Road: A26, A21 8kms away and A1 30kms away
- Air: Lille-Lesquin 45 minutes, Bruxelles 2h, Roissy Charles de Gaulle 1h45
- TGV Station: Béthune TGV station 6 km, Nœux-les-Mines TGV station 2 km
- River port: Béthune river port 8 km
Utilities :
- Digital: Fibre optic
Comments :
A major work force close by: 800,000 inhabitants less than 30km away.
Different projects currently being considered to make LogisterA26 a benchmark in logistics parks.
¼ of those employed privately work in the industry.
A secure HGV parking lot, located over 5ha.
Site opened in 2018.

Albert | 12 ha
Henry Potez Activity Zone
Total surface area : 50 ha
Available surface : 12 ha
Cut out : from 4 000m²
Availability : Immediately
Infrastructures :
- Road: A1-A2 (15 km), A16 (25 km)
- Air: Paris Charles de Gaulle (132 km)
- TGV Station: TGV Haute Picardie (20 km), Arras (36 km)
Utilities :
- Water: drinkable
- Electricity: electrical substation on site
- Gas: GRT (gas provider) on site
- Sanitation: collective
- Digital: Fibre optic
Comments :
Regional aid zone

Steenvoorde | 5,5 ha
“Pays des Géants” Business Park
Total surface area : 7 ha
Available surface : 5,5 ha
Cut out : from 3 200m²
Availability : Immediately
Buildable height : 12 - 14 m
Infrastructures :
- Road: A25 (1km)
- Air: Lille – Lesquin 51 km (35 mn)
- TGV Station: Hazebrouck (12 km / 14 mn), Lille Europe (46 km / 33 mn)
- Canal access: Arques (26 km / 28 mn)
- Sea port: Dunkirk (38 km / 30 mn)
- Riverport: Arques (26 km / 28 mn)
Utilities :
- Water: 80 m3 available per hour
- Electricity: 119 to 250 kVa
- Gas: natural gas, 380 m3/hour
- Sanitation: public network
- Digital: Fibre optic
Comments :
CFE tax exemption voted by the intermunicipality as part of the investment aid for SMEs

Vervins | 40 ha
Créapole Business Park
Total surface area : 65 ha
Available surface : 40 ha
Cut out : on demand
Availability : Immediately
Buildable height : 10 m
Infrastructures :
- Road: RN2 on site, A26 (50 mn), A304 (45mn)
- Air: Paris Charles de Gaulle (2h30), Charleroi (1h30)
- TGV Station: TGV Haute-Picardie (1h20), Champagne TGV (1h15)
- Canal access: Seine–Nord Europe Canal (1h30)
- Rail freight: Saint-Quentin (1h)
- Sea port: Dunkirk (3h), Anvers (3h)
- Riverport: Hautmont (1h)
Utilities :
- Water: 200 to 300m3 available per day
- Electricity: power greater than 250 kva
- Gas: 4 bars pressure
- Sanitation: domestic waste on public network, industrial waste to be treated on site
- Digital: Fibre optic
Comments :
In the regional assistance (AFR) and rural revitalization (ZRR) zones

La Capelle | 5 ha
Les Andiers Business Park
Total surface area : 12 ha
Available surface : 5 ha
Cut out : on demand
Availability : Immediately
Buildable height : 12 m
Infrastructures :
- Road: RN2 on site, A26 (50 mn), A304 (45mn)
- Air: Paris Charles de Gaulle (2h30), Charleroi (1h30)
- TGV Station: TGV Haute-Picardie (1h20), Champagne TGV (1h45)
- Canal access: Seine–Nord Europe Canal (1h45)
- Rail freight: Saint-Quentin (1h)
- Sea port: Dunkirk (3h), Anvers (3h)
- Riverport: Hautmont (1h)
Utilities :
- Water: 200 to 300m3 available per day
- Electricity: power greater than 250 kva
- Gas: 4 bars pressure
- Sanitation: domestic waste on public network, industrial waste to be treated on site
- Digital: Fibre optic
Comments :
In the regional assistance (AFR) and rural revitalization (ZRR) zones

Tergnier | 80 ha
Chauny-Tergnier-La Fere Activity Park
Total surface area : 80 ha
Available surface : 80 ha
Cut out : up to 8 ha
Availability : Immediately
Buildable height : 20 m
Infrastructures :
- Road: A26 (18 km)
- Air: Paris Charles de Gaulle (110 km)
- TGV Station: Tergnier (3 km), Chauny (9 km), TGV Haute-Picardie (60 km)
- Canal access: Sambre to Oise canal, Beautor (7 km)
- Rail freight : Branch line on site
Utilities :
- Water: Industrial
- Electricity: High Voltage (63 kV+), Medium Voltage (20 kV)
- Gas: 4 bars pressure, 99 650 000 kWh/h
- Sanitation: Collective
- Digital: Fibre optic
Comments : In the regional assistance (AFR) zone

Trosly-Breuil | 7 ha
Lamotte Industrial Park
Total surface area : 45 ha
Available surface : 7 ha
Cut out : up to 4 ha
Availability : Immediately
Buildable height : 100 m
Infrastructures :
- Road: A1 (15 mn)
- Air: Paris Charles de Gaule and Paris-Beauvais (1h)
- TGV Station: Compiègne (15 km)
- Canal access: On-site waterway
- Rail freight: SNCF capillary line on site
Utilities :
- Water: Industrial
- Electricity: 63 kV / 20 kV
- Gas: 78 mWh/h
- Sanitation: Biological Wastewater Treatment (eq. 350 000 inhabitants)
- Digital: Fibre optic
Comments : Shared services on site In the regional assistance (AFR) and rural revitalization (ZRR) zones Several ICPE activities classified as high threshold SEVESO are present on the site
Itancourt | 6,9 ha
Le Bordeau Business Park
Total surface area : 6,9 ha
Available surface : 6,9 ha
Cut out : up to 2.6 ha
Availability : Immediately
Buildable height : 15 m
Infrastructures :
- Road: A26 (3 km), A29 (5 km)
- Air: Paris Charles de Gaulle (1h30), Lille-Lesquin (1h), Paris-Beauvais (1h30)
- TGV Station: Haute-Picardie (35 min)
- Rail freight: Tergnier (10 km)
Utilities :
- Electricity: 250 kVa
- Gas: Possible access
- Digital: Fibre optic
Environmental standards : Development permit. No environmental studies conducted.
Comments : The ground surface area of the buildings shall not exceed 60% of the total surface area of the land unit. The absolute height of the constructions that can be implanted at less than 50 meters from the RD 576 shall not exceed 8 meters.
Urvillers | 4,2 ha
L’Epinette Business Park
Total surface area : 4,2 ha
Available surface : 4,2 ha
Cut out : possible
Availability : Immediately
Buildable height : 12 m
Infrastructures :
- Road: A26 (3 km), A29 (5 km)
- Air: Paris Charles de Gaulle (1h30), Lille-Lesquin (1h), Paris-Beauvais (1h30)
- TGV Station: Haute-Picardie (35 min)
- Rail freight: Tergnier (10 km)
Utilities :
- Electricity: 2 x 250 kVa
- Gas: Possible access
- Digital: Fibre optic
Environmental standards : Impact study (2007) and Water Law report(2010)
Comments : The ground surface of the projected units shall not represent more than 60% of the total surface of the land unit.

Le Plessis-Belleville / Silly-le-Long | 30 ha
ZAEI Silly/Plessis
Total surface area : 30 ha
Available surface : 30 ha
Cut out : on demande
Availability : Immediately
Buildable height : 15 or 18 m
Infrastructures :
- Road: direct and free access to RN2
- Air: Paris Roissy Charles de Gaulle (15 mn)
- TGV Station: Paris Roissy Charles de Gaulle (15 mn)
- Rail freight: possibility of branch line
Utilities :
- Water: yes
- Electricity: yes
- Gas: to be decided
- Sanitation: yes
- Digital: yes
Comments : Development of a business park with direct access to the RN2, 15 minutes from Roissy CDG. Several plots of land available for industrial and logistics companies, from SMEs to large groups. The municipalities of Plessis-Belleville and Lagny-le-Sec offer numerous services (restaurants, hotels, day care centers, cultural and leisure activities, SNCF and Transilien train stations).

Hesdin-l'Abbé | 44 ha
Landacres Business Park
Total surface area : 170 ha
Available surface : 44 ha
Cut out : starting from 2,000 m²
Availability : Immediately
Buildable height : 15 m
Infrastructures :
- Road: A16 on site, A26 (50 km), A28 (70 km)
- Air: Lille Lesquin (1h30)
- TGV Station: Calais Fréthun (35 km)
- Sea port: Boulogne-sur-Mer (7 km)
Utilities :
- Water: yes (non industrial)
- Electricity: High Voltage (63 kV+), Medium Voltage (20 kV)
- Gas: yes
- Sanitation: Collective
- Digital: Fibre optic
Comments : Park certified Iso 140001 since 1998 and labeled in 2021 by the Ministry of Economy "Turnkey industrial site".
Loon-Plage | 44 ha
Dunkirk’s International Logistics Zone (to rent)
Total surface area : 145 ha
Available surface : 44 ha
Cut out : up to 33,8 ha
Availability : Immediately
Buildable height : 80 m
Infrastructures :
- Road: A16 (5 km), A26 and A25 nearby
- Air: Lille (1h00), Bruxelles (1h30), Roissy Charles de Gaulle (2h20)
- TGV Station: Dunkirk (5 min)
- Rail freight: Branch line on site
- Sea port: Dunkirk, nearby
- River port:
Utilities :
- Water: Drinkable and industrial
- Electricity: High Voltage (63 kV+), Medium Voltage (20 kV)
- Gas: Can be connected up to 70 bar
- Sanitation: Autonomous
- Digital: Fibre optic
Comments :
In the regional assistance (AFR) zone
Labeled in 2021 by the Ministry of Economy “Turnkey industrial site”.
No limitation on building height
No constraints on constructability

Caudry | 4,29 ha
Vallée d’Hérie Activity Zone
Total surface area : 35 ha
Available surface : 4,29 ha
Cut out : Possible
Availability : Immediately
Buildable height : 18 m
Infrastructures :
- Road: A2 (15 km), A26 (20 km)
- Air: Lille - Lesquin (1h15), Charleroi (1h30), Roissy CDG (2h), Bruxelles Zaventem (1h45)
- TGV Station: Valenciennes (45 min), TGV Haute-Picardie (1h)
- Canal access: Seine-North-Europe canal
Utilities :
- Water: non industrial
- Electricity: High voltage (63kV +)
- Sanitation: Collective
Comments : In the regional assistance (AFR) zone

Buigny - Saint - Maclou | 1,9 ha
Aerodrome business park
Total surface area : 3,8 ha
Available surface : 1,9 ha
Cut out : 9 990 + 6 266 + 3 000 m²
Availability : Immediately
Buildable height : 10 m
Infrastructures :
- Road: immediate proximity to the A16
- Air: Lille - Lesquin and Roissy - CDG 1h45
- TGV Station: Haute Picardie 1h
- Rail freight : Abbeville 11 km
Utilities :
- Water: yes
- Electricity: yes
- Gas: yes
- Sanitation: No, collective to be planned
- Digital: Fibre optic planned

Feignies | 12 ha
La Marlière Business Zone
Total surface area : 35 ha
Available surface : 12 ha
Cut out : from 2 800 m²
Availability : Half 2022
Infrastructures :
- Road: Motorways
- Air: Paris-Charles de Gaulle (2h30), Lille Lesquin (1h), Charleroi (30 mn)
- TGV Station: Valenciennes station 35km away.
Utilities :
- Water: Drinkable
- Electricity: 3,254 KVA installed – source substation 3km away
- Gas: Yes – DN 100
- Sanitation: Collective
- Digital: Fibre

Roubaix | 2,57 ha
Lainière Nord Eclair
Total surface area : 2,57 ha
Available surface : 2,57 ha
Availability : Immediately
Buildable height : 22 m
Infrastructures :
- Road: A22 & A1 on site
- Air: Lille Lesquin 20 km (25 mn)
- TGV Station: Lille Europe & Lille Flandres 13 km (15 to 20 mn)
- River port: Port of Lille 20 km (25 mn)
Utilities :
- Water: Industrial
- Electricity: medium voltage (20 kV)
- Gas: yes
- Sanitation: Collective
Comments : In the regional assistance (AFR) zone

Masnières | 7 ha
Hauts de Masnières Business Park
Total surface area : 11,5 ha
Available surface : 7 ha
Cut out : 2 x 0,85 + 5,25 ha
Availability : Immediately
Buildable height : 20 m
Infrastructures :
- Road: A1, A2 & A26 8 km away
- Air: Lille – Lesquin 65 km, Roissy – CDG 160 km, Bruxelles – Zaventem 150 km
- TGV Station: Arras 40 km, Valenciennes 40 km, Haute Picardie 44 km
- Rail freight : Cambrai 11 km
- Sea port: Dunkerque 140 km
- River port: Marquion 18 km
Utilities :
- Electricity: High voltage (63 kV and +), Medium voltage (20 kV)
- Gas: 125 mm pipeline delivering 4 gigawatts a year
- Digital: Fibre optic
Environmental standards : HQE
Comments :
In the regional assistance (AFR) zone

Arques | 9 ha
Aa Multimodal Gateway
Total surface area : 160 ha
Available surface : 9 ha
Cut out : 1 to 9 ha
Availability : Immediately
Buildable height : 50 m
Infrastructures :
- Road: A26 (10 Km), A25 (25 Km), A16 (37 Km)
- Air: Calais business airport 51 km / 43 minutes, Lille- Lesquin 67 km / 57 minutes
- TGV Station: Hazebrouck 16 km
- Canal access: on site
- Rail freight : Hazebrouck 16 km
- Sea port: Dunkerque (48 Km)
- River port: Arques, on site
Utilities :
- Water: non industrial
- Electricity: 6 MW, expandable to 10 MW
- Gas: 1500 m3/h
- Sanitation: Collective
- Digital: Fibre optic
Environmental standards : Impact study : 2003

Leulinghem | 4,6 ha
Littoral Gateway
Total surface area : 4,6 ha
Available surface : 4,6 ha
Cut out : 2 + 1 + 1,6 ha
Availability : Immediately
Buildable height : 15 m
Infrastructures :
- Road: A26 on site, A25 40 km, A16 32 km
- Air: Calais business airport 40 km (28 mn), Lille Lesquin 98 km (63 mn)
- TGV Station: Frethun 45 km (30 mn), Hazebrouck 32 km (34 mn)
- Sea port: Calais, Boulogne sur Mer and Dunkirk (between 20 and 45 minutes)
- River port: Arques 16 km (14 mn)
Utilities :
- Electricity: Medium voltage (20 kV)
- Gas: possible, medium pressure
- Sanitation: collective
Comments :
In the regional assistance (AFR) zone

Nouvelle-Église | 22,3 ha
Opal Gate
Total surface area : 30 ha
Available surface : 22,3 ha
Cut out : from 2000 m² to 4,42 ha
Availability : Immediately
Buildable height : 6 to 20 m
Infrastructures :
- Road: A16 on site, A25 23 km, A26 11 km
- Air: Calais business airport 10km (10 mn), Lille Lesquin 103 km (1h15)
- TGV Station: Frethun 24 km (19 mn), Dunkirk 29 km (26 mn)
- Sea port: Calais, Boulogne sur Mer and Dunkirk (between 20 and 45 minutes)
- River port: Arques and Dunkirk (25 to 45 mn)
Utilities :
- Water: yes
- Electricity: medium voltage (20 kV)
- Gas: under study
- Sanitation: collective
- Digital: Fibre optic
Comments :
In the regional assistance (AFR) zone

Saint-Quentin-la-Motte-Croix-au-Bailly, Oust-Marest | 30 ha
Bresle Maritime Business Park
Total surface area : 138 ha
Available surface : 30 ha
Cut out : Up to 15 ha
Availability : Immediately
Buildable height : 12 to 40 m
Infrastructures :
- Road: A28 / A16 / A29 20 kms – 20 min
- Air: Roissy Charles de Gaulle (2h), Orly (2h30), Lille (2 h), Beauvais (1h30)
- TGV Station: Haute Picardie (1h30)
- Rail freight: Dieppe, Abbeville (30 min)
- Sea port: Le Tréport (5 min), Dieppe (30 min), Amiens (1h), Rouen (1 h), Boulogne (1h), Calais (1h30), Le Havre (2h)
Utilities :
- Water: drinkable & industrial
- Electricity: Medium Voltage (20kV, upgrade possible
- Gas: Yes
- Sanitation: Collective
- Digital: Fibre optic
Comments :
In the regional assistance (AFR) zone, revitalisation fund available

Famars | 6,9 ha
Transalley Business Park
Total surface area : 34 ha
Available surface : 6,9 ha
Cut out : from 3259m² to 3,5 ha
Availability : Immediately
Buildable height : 15 m
Infrastructures :
- Road: A2 (5 mn away)
- Air: Lille 55km (35 min), Paris 190km (2h), Brussels 106km (1h15), Charleroi 86km (45min)
- TGV Station: Valenciennes (4 km)
- Canal access: Bruay-Saint-Saulve 15 min
Utilities :
- Water: drinkable
- Electricity: High Voltage (63 kV and+), 4 Mw (upgrade possible)
- Gas: High pressure
- Sanitation: Collective
- Digital: Fibre optic
Comments :
In the regional assistance (AFR) zone

Barenton-Bugny | 4 ha
Griffon business park
Total surface area : 150 ha
Available surface : 4 ha
Cut out : Up to 3 ha
Availability : Immediately
Buildable height : 12 m
Infrastructures :
- Road: A26 less than 1 km away, N2 nearby
- Air: Roissy Charles de Gaulle (1h)
- TGV Station: Reims Bezannes (40 mn)
Utilities :
- Water: Yes (non industrial)
- Electricity: High voltage (63 kV and +), medium voltage (20 kV)
- Gas: 3 600m3/h
- Sanitation: Collective
- Digital: Fibre optic
Comments :
In the regional assistance (AFR & ZRR) zones

Roubaix Tourcoing Wattrelos | 20 ha
Union
Total surface area : 80 ha
Available surface : 20 ha
Availability : Immediately
Buildable height : 21m, in parts 36 m
Infrastructures :
- Road: Urban freeway and A22 (Belgium)
- Air: Lille Lesquin 30min by road/ Roissy 1hr10 by TGV
- TGV Station: Tourcoing and Lille
- Canal access: Roubaix Canal (pleasure)
Utilities :
- Water: Drinking water on site
- Sanitation: separate
- Digital: fibre
Comments :
200,000m² FLOOR SPACE
3 underground stations, Lille Metropole ecodistrict, industrial site undergoing urban reconditioning

Thélus | 6,5 ha
Les Meuniers Business Park
Total surface area : 15 ha
Available surface : 6,5 ha
Cut out : from 2,000m² to 20,000m²
Availability : Immediately
Infrastructures :
- Road: 1km from A26
- Air: 44km from Lille airport
- TGV Station: 9km from Arras TGV station
Utilities :
- Digital: Fibre optic
Comments :
Land available for construction

Bully-les-Mines / Aix-Noulette | 9 ha
Alouette Business Park
Total surface area : 147 ha
Available surface : 9 ha
Cut out : 2 lots of 4 and 5ha
Availability : Immediately
Buildable height : Bully : 25m and Aix : 12 m
Infrastructures :
- Road: A21: 500m/ A26: 3km / A1: 20km
- Air: Lesquin: 30km / Roissy: 160km / Brussels: 150km
- TGV Station: Lens: 5km
- Rail freight: Lens: 5km
- Sea port: Boulogne-Calais: 85km / Dunkerque: 75km
- River port: River Port Harnes: 10km / Béthune: 15km
Utilities :
- Water: Drinking water
- Electricity: yes
- Gaz: yes
- Sanitation: Rainwater: by plot
- Digital: fibre optic
Comments :
Located in the heart of the Alouette Business Park’s recent 80ha extension (the Park was originally just 67ha), at the foot of the Artois hills and ideally situated near a significant population base (>640,000 inhabitants)

Illies - Salomé | 14,8 ha
Logistics building Illies Salomé
Total surface area : 148,000m² to rent ha
Available surface : 14,8 ha
Cut out : from 12,000m²
Availability : Provisional delivery of first 100,000m² logistic building at the end of 1st quarter 2022
Buildable height : 11,6 m
Infrastructures :
- Road: N41/ N47: 300m
- Air: Lesquin: 29kms
- TGV Station: 23kms to Lille europe
Comments :
The company PRD is the main developer, building permit for first buiding obtained, environmental protection authorisation to operate

Estrées-Deniécourt | 50 ha
Haute Picardie Business Cluster
Total surface area : 50 ha
Available surface : 50 ha
Cut out : from 1 to 20ha
Availability : Immediately
Infrastructures :
- Road: A1 1km away and access to A29 directly on site
- Air: Paris-Charles de Gaulle Airport: 105km
- TGV Station: Haute Picardie TGV Station onsite
Utilities :
- Water: Drinking, industrial
- Electricity: Debit available currently 3,000kW/h and will soon be increased to 5,000.
- Gas: Present on site but without direct access to GRT gas network
- Sanitation: Collective
- Digital: Fibre

Hordain | 16 ha
Hordain Hainaut Business Park
Total surface area : 16 ha
Available surface : 16 ha
Cut out : From 2ha
Availability : Immediately
Buildable height : 25 m
Infrastructures :
- Road: Access to A2 directly from the park
- Air: 55km to Lille Airport, 130km to Brussels Airport, 165km to Paris CDG Airport
- TGV Station: Valencienne 24km
- Canal access: River port (freight) on the wide-gauge canal: 5km (Bouchain)
- Rail freight: Rail track in park or station 3km away (Bouchain)
- Sea port: 145km (Dunkirk)
Utilities :
- Water: Drinking
- Electricity: 8 Mw, additional power possible
- Gas: GRDF Network 4 bars + 14 bar network in proximity
- Sanitation: Collective
- Digital: Fibre

Dunkerque | 50 ha
Port of Dunkirk
Total surface area : 50 ha
Available surface : 50 ha
Cut out : from 10ha
Availability : Immediately
Infrastructures :
- Road: Motorways (A16/E40, A25 and A26)
- TGV Station: TGV to Lille (30 min) and Paris (1h30)
- Rail freight: Freight rail station
Utilities :
- Water: Drinkable and industrial
- Electricity: Dedicated source substation connected to RTE networks “Warrande” and “Grande-Synthe” for requirements up to 25MW
- Gas: Up to 70 bars of pressure to the edge of the site.
- Sanitation: Collective. Several treatment stations (equivalent to more than 150,000 inhabitants)
- Digital: Fibre. Site located 8 km from OVH Cloud data centre (500,000 server capacity)
Comments :
Labeled in 2021 by the Ministry of Economy “Turnkey industrial site”.

Méaulte | 59 ha
Aéropole de Picardie
Total surface area : 59 ha
Available surface : 59 ha
Cut out : starting from 3 ha
Availability : Immediately
Infrastructures :
- Road: A1-A2 motorways: 15km; A16: 25km
- TGV Station: Haute Picardie TGV Station (for Roissy and France) : 20km; Arras TGV Station (for Paris-centre), direct train from Albert: 20min
Utilities :
- Water: Drinking
- Electricity: Source substation in Albert with 6 megawatts brought to the Industrial Park
- Gas: Yes
- Sanitation: Collective. Except for large food industry which may build its own wastewater treatment plant onsite.
- Digital: Fibre

Beauvais / Tillé | 120 ha
Novaparc
Total surface area : 125 ha
Available surface : 120 ha
Cut out : from 2,000m²
Availability : Immediate reservations/construction starting early 2021
Buildable height : 12 m
Infrastructures :
- Road: A16 motorway 2 min away
- Air: Paris Beauvais International Airport 2 minutes
- TGV Station: Beauvais station
Utilities :
- Water: Diameter 150 to 200mm (4 bars pressure)
- Electricity: Low voltage and medium voltage
- Gas: HDPE calibre 160 and 200 (4 bars pressure)
- Sanitation: Separate network
- Digital: Fibre optic France Télécom - ADSL
Comments : Novaparc : A business park located next to Beauvais International Airport, 50 minutes from Paris. 125 hectares available.

Onnaing | 85 ha
Onnaing / Vallée de l’Escaut II (PAVE II) Pusiness Park
Total surface area : 120 ha
Available surface : 85 ha
Cut out : 80 ha + 2 ha + 3 ha
Availability : End of 2021
Buildable height : 25 m
Infrastructures :
- Road: A2 (Paris - Bruxelles) interchange on site
- Air: Prouvy aerodrome (15km)
- TGV Station: Valenciennes (8km)
- Rail freight: Valenciennes (8km)
- River port: Saint-Saulve Container Port (5km)
Utilities :
- Water: Industrial and drinking
- Electricity: High and medium voltage
- Gas: High pressiure
- Sanitation: Separate networks
- Digital: Fibre possible
Comments : The PAVEII extension is for industrial and logistics purposes. Toyota, Barilla and Sanoh are already present.

Roubaix et Tourcoing | 11,2 ha
La Lainière
Total surface area : 33 ha
Available surface : 11,2 ha
Cut out : yes
Availability : Immediate availability on plots PA8, L8, PF2, mid-term for plots PF3, PF4, PF1, L1, L2, PA4, PA6, other plots already sold
Infrastructures :
- Road: yes
- Air: no
- TGV Station: no
- Canal access: yes
- Rail freight: no
- Sea port: no
- River port: no
Utilities :
- Water: yes
- Electricity: yes
- Gas: yes
- Sanitation: yes
- Digital: yes

Soissons | 33 ha
Le Plateau Business Park
Total surface area : 150 ha
Available surface : 33 ha
Cut out : Plots can be modulated from 10,000m²
Availability : Immediately : 12,000 and 15,000m². 2022: 55/60ha
Buildable height : depending on position in park, 20 m
Infrastructures :
- Road: Direct access to N2. Junction with A1/A4 and A26 30 minutes away
- Air: Paris Roissy CDG International Airport 45 min
- TGV Station: Paris-CDG and Marne la Vallée 40 min
Utilities :
- Water: 2,000 m3/day, 144m3/h, pressure 5,5 bars
- Electricity: MT/BT network, 7+7 MVA (2 lines)+2 MVA extension (3rd line)
- Gas: 25 GWh/year (pressure 4 bars)
- Sanitation: Separate network, water treatment plant nearby
- Digital: fibre optic
Comments : Industrial/logistics park less than 1h from Paris Roissy CDG airport - public transport - landscape integration (Environmental Specifications). In the regional assistance (AFR) zone

Le Cateau Cambresis | 25 ha
Quatre-Vaux Business Park
Total surface area : 25 ha
Available surface : 25 ha
Cut out : Possible
Availability : Immediately
Buildable height : 12 m
Infrastructures :
- Road: A2 motorway 25km away
- Air: Lille-Lesquin 75km, Bruxelles-Zaventem 130km and Roissy-CDG 180km
- TGV Station: Valenciennes 30km
- Canal access: Canal Seine Nord Europe (en projet) à 40km
- Rail freight: Valenciennes à 30km
- Sea port: Dunkirk 40km
- River port: Saint-Saulve 40km
Utilities :
- Electricity: 1 MW
- Digital: Fibre optic
Comments : Quatre-Vaux Business Park in Cateau-Cambrésis has 25 hectares of land available for industrial and logistics operations.

Cambrai | 320 ha
E-Valley Business Park
Total surface area : 320 ha
Available surface : 320 ha
Availability : Immediately
Buildable height : 22 m
Infrastructures :
- Road: Direct access to motorways A26 and A2
- Air: Lille-Lesquin 55km, Roissy-CDG 155km and Bruxelles-Zaventem 150 km
- TGV Station: Douai 22 km, Arras 30 km
- Canal access: Seine Nord Europe Canal (project underay)
- Rail freight: Rail link (project underway)
- Sea port: Dunkerque 140 km
- River port: Marquion 1,5 km
Utilities :
- Water: 250m3/h
- Electricity: 110MVA in 2024 with 10MVA (Secure electrical transmission system)
- Gas: liquid and compressed
- Digital: Fibre optic
Comments : Airbus drone transport. The E-Valley Business Park is exceptionally well located: connected to the A26 and close to 8 major motorways (A1, A2, A16, A21, A22, A25, A26 and A29); there is a project to connect the site and the Cambrai-Marquion multi-modal platform to the national rail network; an air transport dimension for business flights; and, in time, wide-guage river access to the major Northern European ports via the Seine Nord Europe Canal.

Iwuy | 15 ha
Val de Calvigny Business Park
Total surface area : 45 ha
Available surface : 15 ha
Cut out : Possible
Availability : Immediately
Buildable height : 28 m
Infrastructures :
- Road: Direct access to A2 motorway
- Air: Lille-Lesquin 60km away, Roissy-CDG 160km, and Bruxelles-Zaventem 130km
- TGV Station: Valenciennes 22km, Douai 35km
- Canal access: Seine Nord Europe Canal (in development) 22km away
- Rail freight: Cambrai 10km
- Sea port: Dunkirk 145km
- River port: Bouchain 5km
Utilities :
- Water: 50 m3/h
- Electricity: (power available) : 20,000 kVA
- Digital: Fibre optic
Comments : The Val de Calvigny Business Park is located in Iwuy between Cambrai and Valenciennes and is connected to the A2 Paris -Bruxelles motorway. With the A2 on its doorstep, this site offers excellent quality of service for all logistics and production projects. Babyliss has set up its European Distribution Centre here. The presence of Sevelnord (the Peugeot-Citroën–Fiat factory) just a few metres away is an asset for sub-contractors and activities complementary to the automotive industry.

Saint-Quentin | 42 ha
Autoroutes Business Park
Total surface area : 110 ha
Available surface : 42 ha
Cut out : Yes
Availability : Immediately
Buildable height : 20 m
Infrastructures :
- Road: A26 A29 (A1) 2 minutes away
- Air: Lille Lesquin (1h) Roissy (80min) Beauvais (80min)
- TGV Station: 25min
- Rail freight: 5min
- Sea port: Dunkirk (2h)
- River port: Saint-Quentin
Utilities :
- Water: 20 m3/hour
- Electricity: 6,000 kw
- Gas: 4 bars 1,500 m3/h
- Digital: High speed
Comments : On the outskirts of Saint-Quentin and close to the main motorways A26, A1 and A29, this business park offers investors and ideal location to encourage development in the European market. The business park can accommodate any industrial, artisanal or commercial projects.

Croixrault | 25 ha
Mine d’Or Business Park
Total surface area : 87 ha
Available surface : 25 ha
Availability : Immediately
Buildable height : 40 m
Infrastructures :
- Road: A29 Motorway le Havre-Rouen-Amiens. Exit 13
- Air: 45 minutes Beauvais, 1.5 hours Charles de Gaulle
Utilities :
- Water: >100m3
- Electricity: Volts > 8MWH
- Gas: > 25 MWH
- Sanitation: Collective
- Digital: Fibre optic
Comments : Water park with 400 users/day, leisure centre with 150,000 visitors expected/year. JJA (logistics platform for the home and garden sector)

Le Bosquel | 23 ha
Bosquel Business Zone
Total surface area : 45 ha
Available surface : 23 ha
Availability : Immediately
Buildable height : 15 m
Infrastructures :
- Road: A16 exit 17
- Air: 25 min to Beauvais, 1h to Charles de Gaulle
Utilities :
- Water: yes
- Electricity: yes
Comments : The area will be serviced according to project holders' needs. The Commune of Somme Sud-Ouest can acquire new plots quickly. A16 : 15,000 vehicules/day of which 1,200 are HGV (motorway exit opposite zone) €10/m²

Wancourt | 7 ha
Artoipole 2
Total surface area : 175 ha
Available surface : 7 ha
Cut out : Between 5,000m² and 20,000m²
Availability : Immediately
Infrastructures :
- Road: Direct access to A1
- Air: 44km to Lille airport
- TGV Station: 8kms to Arras TGV train station
Utilities :
- Digital: Fibre optic
Environmental standards : ICPE standards
Comments : 62 companies representing approximately 2,750 jobs and €1,700 million of private investment for 215,000 m2 of buildings in service. Of these 62 companies, 11 are foreign:
- 3 with Belgian capital (Vandemoortele, Verduyn, Soup’idéale);
- 2 with American capital (Pitney Bowes mail services, XPO Logistics);
- 1 with Japanese capital (Akebono brake pad manufacture);
- 1 with Italian capital (Plastam plastic injection);
- 1 with Dutch capital (Desmazières potato plants);
- 1 with German capital (Grimme agricultural machinery).
- 21 companies in logistics and transport;
- 11 in the food industry;
- 9 in metallurgy;
- 21 in various sectors, including three major production areas: printing, isothermic containers and plastics.

Saint-Laurent Blangy | 21 ha
Actiparc
Total surface area : 280 ha
Available surface : 21 ha
Cut out : between 5,000m² and 50,000m²
Availability : Immediately
Infrastructures :
- Road: 9 km from A1 motorway
- Air: 43 km from Lille airport
- TGV Station: 6 km from Arras TGV train station
Utilities :
- Digital: Fibre optic
Environmental standards : ICPE standards
Comments : 31 companies in operation since 1 September 2018, representing more than 1,500 jobs, €575 million of private investment and 188,000m2 of buildings. Of these 31 companies, 4 are foreign:
- 2 with Belgian capital: Vandemoortele (manufacturing frozen pre-baked bread) and Agrafresh (vegetable processing);
- 1 with Norwegian capital: Leroy Fishcut (fish processing);
- 1with Japanese capital: Shimano (bicycles, French head office)

Blaringhem | 21 ha
Blaringhem
Total surface area : 43 ha
Available surface : 21 ha
Cut out : Plot division possible
Availability : Immediately, disused industrial land already built on
Buildable height : 35 m
Infrastructures :
- Road: A26 13 km 16 min/A25 32 km 30 min/D943 HGV Accesss
- Air: Lille Lesquin 67 km 54 min
- TGV Station: Hazebrouck 12 km (15min)
- Canal access: Wide-gauge canal from Neuffosseé linking to the North Sea via thePort of Dunkirk and to the future Seine-North-Europe-Escaut canal.
- Rail freight: Hazebrouck 12 km (15min)
- Sea port: Dunkerque 58 km (43 min)
- River port: Arques 8km 11 min/Béthune/Garbecque
Utilities :
- Water: Awaiting information
- Electricity: 26 MVA extendable, 90000V substation onsite
- Gas: Network onsite
- Sanitation: Must be autonomous
- Digital: Fibre along canal
Comments : This site is intended for food industry and related activities